Activity Duration

Venkataramiah S Annapragada
23/12/2018 0 0

Number of work periods needed to complete the activity.
Duration of an activity is calculated using the Task Rule which is as follows :

             Work = Duration * Resource Units

i.Work is the Effort estimated for the activity. Various Estimation techniques discussed previously can be used. This is usually expressed in hours.

ii.Resource Units equals the number of resources that are assigned to the activity and the number of hours per day they are available for this activity.

iii.Duration calculated from above Rule is usually expressed in days.

Example :

An High Level Design Document is required to be prepared. It’s estimated effort is 40 hours. Two resources are assigned to it. Both of them can spare 4 hours each daily for this activity. What is the Duration of this Activity ?

0 Dislike
Follow 1

Please Enter a comment

Submit

Other Lessons for You

Requirements Traceability Matrix
To keep a trace of the requirements captured till they are implemented Traceability helps in the following : Keeping track of requirements as they move through various project phases Identifying...

Control Charts
Used to determine if process is stable or unstable Upper Control Limit and Lower Control Limit are set by process. These denote the statistical boundaries within which the process should operate...

Project Management Business Documents
Project Business Case It documents the economic feasibility of the project. It is prepared before starting the project and can result in a go/no-go decision for the project. One of the criteria for determining...

Agreements
A contract is a mutually binding agreement. It obligates the seller to provide the deliverables and the buyer to make the payment on delivery. It is a legal document recognised in the court of law The...

Critical Path Method [CPM]
This method involves the following steps : Calculate the Duration for all activities on the Task Network Diagram. Calculate the early start , early finish , late start and Late Finish for all activities...
X

Looking for PMP Training Classes?

The best tutors for PMP Training Classes are on UrbanPro

  • Select the best Tutor
  • Book & Attend a Free Demo
  • Pay and start Learning

Learn PMP Training with the Best Tutors

The best Tutors for PMP Training Classes are on UrbanPro

This website uses cookies

We use cookies to improve user experience. Choose what cookies you allow us to use. You can read more about our Cookie Policy in our Privacy Policy

Accept All
Decline All

UrbanPro.com is India's largest network of most trusted tutors and institutes. Over 55 lakh students rely on UrbanPro.com, to fulfill their learning requirements across 1,000+ categories. Using UrbanPro.com, parents, and students can compare multiple Tutors and Institutes and choose the one that best suits their requirements. More than 7.5 lakh verified Tutors and Institutes are helping millions of students every day and growing their tutoring business on UrbanPro.com. Whether you are looking for a tutor to learn mathematics, a German language trainer to brush up your German language skills or an institute to upgrade your IT skills, we have got the best selection of Tutors and Training Institutes for you. Read more